We value our content and access to our full site is only available with a subscription . In addition, your subscription includes access to digital archive copies from 2006 onwards. The planned six-week closure of Uig Harbour – which commenced on 30 October – is in its final week and considerable progress has been made despite severe weather in November which contained two named storms. These activities require constant crane operations for welding and dive access with crane operations being delayed due to adverse weather. “The Highland Council apologises for any inconvenience caused and will seek to minimise the delay to re-opening services.”A weekly update will continue to be provided on the Councils website at www.highland.gov.uk/info/1523/transport_and_streets/832/uig_harbour_redevelopment.
Source: The Times December 04, 2023 08:02 UTC