At a Tripoli ceremony yesterday, Libyan authorities handed over the Third Ring Road project site to the Egyptian Orascom/ Hassan Allam / Rowad / NRD (O.H.R.N) JV company, with U.S. firm Hill International acting as project managers. Egyptian consortium chosen for their experienceIn his speech, the Prime Minister, confirmed that the stage of clearing the project site has been completed, despite the difficulties faced its implementation. He said today another stage is being inaugurated, which is the handing over of the project site and preparing to start implementation. Ajdabia-Jalo and Ubari-Ghat roadsThe Director of the Transportation Projects Implementation Agency, Sami Al-Abash, then presented the 250 km Ajdabiya – Jalo road project, and the road 360 km Ubari – Ghat road project. In his detailed presentation of the project plan, he explaining the materials included in the project and the 18-month implementation period for the Ajdabiya-Jalo project and 16 months for the Ubari-Ghat project.
Source: Libya Today March 13, 2023 22:14 UTC