General News of Saturday, 8 February 2020Source: Graphic.com.ghTema Motorway Interchange project to be completed on scheduleFile PhotoWork on the $57-million Tema Motorway Interchange project is currently 91 per cent complete and the contractors have given an assurance that it will be delivered by the June 6, 2020 deadline. ObservationsIt was observed that the major works on the project had been done leaving asphalting, road markings, street lights, traffic signals and drainage outstanding. Mr Uemura said other project deliverables left in the scope of work were within the time frame. He said the project was dear to the country and that he expected work to be completed on schedule. BackgroundThe $57-million Tema Motorway Interchange project is being financed under a grant from the Japanese government under its Japanese International Cooperation Agreement (JICA).
Source: GhanaWeb February 08, 2020 11:26 UTC