“Our target is that by 2023, our power generation capacity will reach 10,000 MW,” chief executive Kijja Sripatthangkura said at a press conference yesterday. “In addition to our two domestic deals, this year, we expect to secure at least two more international deals with the aim of finalising five to six overseas deals,” Kijja said. Currently, Ratch Group’s power plants have a power generation capacity of 6,860.34 MW. Meanwhile, four projects under construction will add a combined power generation capacity of 486.79 MW. With all these plants combined, Ratch Group will have total power generation capacity of 7,526.86 MW, leaving the company 2,473.14 MW short of its 2023 target.
Source: The Nation Bangkok May 23, 2019 21:49 UTC