“The fact of the matter is that we have not agreed on any contract variation. Updated Sun, July 10th 2016 at 00:00 GMT +3Kenya Pipeline Company could lose billions of shillings if it accepts a demand for additional funding to cover delays in the project of laying out a new pipeline. The extension was to run from February to May 31, 2016 to enable them finish the pipeline. In January this year, Zakhem requested a Sh4 billion worth of variation of time and cost. Yesterday, company MD Joe Sang confirmed that the extensions of time of up to September — for both line and pumps, were granted at no cost.
Source: Standard Digital July 09, 2016 19:07 UTC