TI Corp head offices in Coquitlam, B.C. TI Corp shelved the review and it was never mentioned again, said the consultants. In a statement KPMG said, "The [Office of the Auditor General] did not direct any particular review process that TI Corp should follow." rules not followedAnother example of "weak oversight" was that TI Corp did not establish an audit committee during construction, say the consultants. $300 million in change ordersFraser Heights Bridge $31 million Bridge built over wetlands in Surrey, sole-sourced to Kiewit Flatiron, then subcontracted.
Source: CBC News September 07, 2017 09:04 UTC