With the installation of the tenth span, 1,500 metres of the bridge will be visible from Zajira point. This photo was taken on Tuesday, April 23, 2019 at Jazira point of Padma Bridge Dhaka TribuneThe 13th span is likely to be installed soonRoad Transport and Bridges Minister Obaidul Quader has said around 67% work of the Padma Bridge has been completed. He said: “Some 76% work of the main bridge has been completed while 55% of the river training and 100% work of the connecting roads are done. Some 1,800 metres of the Padma Bridge are now visible, after the installation of 12th span. The 13th span is likely to be installed in the next few days, he said.
Source: Dhaka Tribune May 20, 2019 10:52 UTC