Business News of Wednesday, 24 August 2016Source: Business in CameroonMengong-Sangmelima road: work completion estimated at 12%File Photo of road constructionDuring the evaluation meeting for the construction of the Mengong-Sangmelima road of 73.658 km, a few days ago in Yaoundé, the Minister of Civil engineering, Emmanuel Nganou Ndjoumessi, declared himself satisfied with the works undertaken on this important road. From the presentation made by the monitoring mission, we can mention that significant progress were noted in the execution of the works. The global progress for May 2016 is estimated at 12% for 31.93% of the time allocated. However, the monitoring mission noted that the rate of progress of the completed works would be higher if some constraints had not delayed the work developments. Several actions have been carried out to solve these different situations and, currently, the company has started removing its equipment to enable the company Arab Contractors start work.
Source: CameroonWeb August 24, 2016 12:13 UTC