KUALA LUMPUR (March 10): The Kuala Lumpur International Airport’s (KLIA) Runway 3 has resumed full operations seven days ahead of schedule. KLIA said improvement works began with a full closure from Feb 24 to 26, followed by operations under a shortened runway configuration while the remaining works progressed. “With the works now completed earlier than planned, the runway has resumed full-length operations ahead of schedule,” it said in an official X posting. It added that the works form part of KLIA’s ongoing efforts to maintain the highest safety and quality standards. The actual scheduled date for resumption was March 17.
Source: The Edge Markets March 10, 2026 09:44 UTC