Former ministers skip Nandipur case hearing


The reference is about inordinate delay in legally vetting the Nandipur power project which led to an increase in the project cost by several billions rupees. During Thursday’s proceedings, a prosecution witness submitted the record related to the reference with Accountability Court Judge Arshad Malik and also recorded his statement. The judge resumed hearing on a reference pertaining to delay in execution of Nandipur Power Project. The Nandipur project was approved by the Economic Coordination Committee of the cabinet on Dec 27, 2007, at a cost of $329 million. The water and power ministry also failed to take any concrete steps to resolve the issue and the matter remained pending.


Source: The Express Tribune March 21, 2019 18:32 UTC