Final tests underway for LRT3 - News Summed Up

Final tests underway for LRT3


The Transport Minister said to date, most train sets have already completed the Fault-Free Run (FFR) tests, which is a crucial component before LRT3, which connects Shah Alam and its surrounding areas, begins operations. Under the FFR test, the trains are required to travel at least 4,000km without a single glitch. To date, two train sets, involving 14 of the 22 trains, have completed the 22-day FFR testing process. Spanning 37.8km, the LRT3 line connects Bandar Utama in Petaling Jaya to Johan Setia in Klang. On the recent incidents of disruption involving the Kelana Jaya LRT Line service, Loke said his ministry is working hard to address the issue.


Source: The Star February 28, 2026 02:36 UTC