“Most of the BRTS work has already been completed on this corridor and we are starting operations from January 1. The work on this stretch got delayed even as the tenders for BRTS work were floated in 2016. However, due to two flyover works located at Swargate and Shankarmaharaj math, the BRTS work got delayed,” said Mohol. In the last two years, PMC had set four deadlines for restarting the BRTS operations, but was not able to kick start the project. Meanwhile, the Nationalist Congress Party (NCP) has demanded inquiry of BRTS work in the city.