Like the floods of Accra that have become a perennial occurrence, residents of Weija have once again had to wake up to the devastating effects of the spillage of the Weija Dam by the Ghana Water Company Limited. The annual spillage of the dam is meant to release excess water from the dam. The maximum level of water the dam is built to hold is about 46 feet, but the level came up to 48 feet, thereby threatening its safety, hence the decision to spill. The management explained further, "the Weija dam is currently at a level of 49.5ft as against the maximum operating level of 48ft. As a result, four (4) spill gates have been opened to safeguard the integrity of the dam, save the dam from collapse, and save lives and properties."


Source:   GhanaWeb
October 04, 2022 20:19 UTC