Track doubling work gets over; awaits inspection


The entire doubling project from Ponmalai to Thanjavur has been completed at a cost of around ₹ 400 crore, said the official. The completion of the track doubling works is now expected to give a push to the ongoing overhead electrification works in the Tiruchi - Thanjavur broad gauge section. The Central Organisation of Railway Electrification (CORE) is presently carrying out electrification works from Tiruchi to Solagampatti. It was awaiting the completion of the track doubling works from Solagampatti to Thanjavur. With doubling works having been completed, the CORE would speed up the overhead electrification works and the plan was to complete electrification works by June, said a CORE official.


Source: The Hindu February 14, 2018 02:15 UTC