Nineteen more Railway ROBs await alignment nod


Zaheerabad-Metalkunta ROB: Joint inspection has to be done to prepare plans afresh after it was proposed to take up four lane bridge with footpaths in the place of proposed two-lane bridge. Adilabad yard ROB with subway: Revised proposals are yet to be submitted after it was realised that the original alignment passes through heavy built up area. Kazipet-Balarshah ROB: Alignment yet to be finalised. Secunderabad-Kazipet: Changed alignment plan still to be submitted after it was decided to hold a joint inspection with National Highway Authorities of India (NHAI) as the proposed alignment runs parallel to the national highway. Mahabubnagar-Manyamkonda ROB: Joint inspection between the R&B and railway engineers to be conducted and alignment still to be finalised.


Source: The Hindu August 12, 2017 18:17 UTC